§2808a is live: 17 military construction projects now run on the new other-transaction authority, and the first award — $169.1M at JBLM — is in

Asked:

“What is the latest on 2808a and using it for construction”

10 U.S.C. §2808a, enacted in the FY2026 NDAA on December 18, 2025, lets military departments build and repair facilities through other transactions instead of FAR contracts. The scan below covers 19 project rows from public procurement notices (two are duplicate listings of the same projects, so 17 distinct projects or programs), current as of September 8, 2026; the latest project notices are mirrored from procurement aggregators — the latest public notices found, not verified final awards.

The §2808a pipeline: latest update by project and stage

Awarded — one so far Solicitation RFI / presolicitation / notice Industry day, active or closed duplicate listing of a project above

Bubble area = stated dollar value where one is published. Values mix awarded, programmed, planning and master-agreement figures — they are not obligations. Projects without a stated value show as small fixed marks. Hover a mark for detail.

What the picture cannot say

The lone public award: a $169.1M facilities-modernization other transaction at Joint Base Lewis-McChord, reported the week of July 23 and dated July 7, 2026 — hklaw.com
Stated values across de-duplicated rows total at least $3.14B, dominated by the $1.4B Sentinel Utility Corridor at Malmstrom AFB and the $986M Multi-Domain Cyber and Intel Operations Center at JBSA-Lackland — cleat.ai
The newest dated notice is the August 27 JBER Fighter Town utilities solicitation; near-term milestones fall on Sep 9 (JBER), Sep 11 (JBSA kennels), Sep 14 (Space Force industry day), Sep 15 (JBLM FSRM) and Sep 24 (Sentinel) — lightrfp.com
An April 29, 2026 infrastructure-acceleration memo directs construction agents to maximize §2808a where speed, flexibility, savings or risk reduction result, and to report use twice a year — defensecommunities.org

How the authority works — and its guardrails

Scope

The Secretary concerned may enter transactions other than contracts, cooperative agreements or grants for facility repair and construction — planning, design, engineering, prototyping, piloting and execution — funded from MILCON, O&M or RDT&E accounts. uscode.house.gov

Cost and scope controls

§2808a is expressly subject to 10 U.S.C. §2853, which limits authorized cost and scope variations; projects must be otherwise authorized by law. hklaw.com

Congressional notice

At least 14 days before each transaction, Congress gets the project title, description and location, estimated cost and funding source, the recipient if known, and the rationale for using this authority. legalize.dev

Follow-on work

A follow-on production contract or transaction without further competition is allowed only if the original transaction was competed and the participants completed a complete and useable facility or improvement. law.cornell.edu

Reporting

The Secretary of Defense must report to the defense committees 180 days after enactment and biannually thereafter: department, cost, funds, scope, delivery-speed differences, savings and lessons learned. law.lawstack.com

Contractor caution

FAR clauses and familiar FAR risk allocations do not automatically apply: labor standards, bonding and payment protection, changes, disputes, IP and data, cybersecurity, insurance, termination and protest forum must be negotiated per opportunity. §2808a does not remove authorization, appropriations, environmental or safety requirements. noah-news.com

Policy chronology

All 19 project rows

ProjectLocationStageLatest updateStated valueNext milestoneSource

Scan of public procurement notices and legal analysis on 10 U.S.C. §2808a, current as of 2026-09-08: 19 project rows (17 distinct projects; two duplicate listings marked), 20 legal-analysis rows and 40 policy rows across lightrfp.com, cleat.ai, app.govly.com, starbridge.ai, hklaw.com, sam.gov and others. Stated values are mixed-stage figures as published — awarded, programmed, planning or master-agreement — not obligations; project details are latest public notices found via aggregators, not verified awards. Some policy rows unrelated to §2808a were cut.

This report was generated automatically by Keenable SELECT at a user's request, from publicly available web sources linked herein. Keenable does not review, verify, or endorse its contents and makes no representation as to accuracy, completeness, or timeliness; AI-based extraction may contain errors. Nothing in this report is investment, legal, financial, or other professional advice. All trademarks and referenced content remain the property of their respective owners; no affiliation or endorsement is implied. To report an error, rights concern, or request removal: legal@keenable.ai.